Skip to main content
Cath Lab Setup · Mumbai

Cath Lab Setup in Mumbai

Mumbai cath labs are almost always cut into occupied buildings, where slab-to-slab height, floor loading and the occupancy on all six sides of the room decide what is possible before anyone draws a layout. We survey, engineer and deliver from our Pune base.

Service
Cath Lab Setup
City
Mumbai, Maharashtra
Our Office
Pune
Site Mobilisation
Site survey in 3 working days

Mumbai raises the specification, and the building pushes back

Mumbai carries one of the deepest interventional cardiology markets in India — several high-volume catheterisation programmes, a dedicated cardiac hospital layer, and public teaching hospitals absorbing much of the emergency coronary load. A hospital adding a lab here enters a market where referrers already know what a good lab looks like.

The predictable effect is upward pressure on specification. Biplane, hard to justify in a smaller city, is genuinely defensible in Mumbai centres doing neurointervention, paediatric and congenital work or complex structural heart cases, because that case mix exists here in volume. So are hybrid rooms for TAVI, EVAR and TEVAR. The honest position is unchanged: single-plane covers the overwhelming majority of adult coronary work, and biplane is argued from a documented case mix, not from what the hospital two kilometres away installed. Nor is it only an imaging line: biplane and hybrid rooms need more barrier area, a bigger technical room, more power and more cooling, all of which cost more here than anywhere else in Maharashtra.

The building decides whether the room is possible

Almost no cath lab here is built on an open site, so the survey is mostly a structural investigation.

Slab-to-slab height is the first gate. A ceiling-mounted gantry wants 3.4-3.6 m slab to slab so the finished ceiling sits near 2.9-3.0 m under the rails; much of the Mumbai hospital estate was built at 3.0-3.3 m. Below about 3.2 m the ceiling gantry is out, and the floor-mounted fallback changes OEM selection, sweep clearance and the anaesthesia position.

Floor loading is the second. Gantry, table plinth and the steel grid carrying monitors, shields and pendants concentrate the OEM point loads into a handful of anchors rather than spreading them, so slabs designed around 3-4 kN/m² live load need checking against that schedule specifically; the usual answer is a steel transfer frame spanning to beams. Cabling to the gantry needs a trench, or a raised floor that consumes height you were already short of.

Getting the equipment in is a genuine logistics exercise. Panels knock down; a gantry stand does not. Lift car dimensions and capacity, staircase turning radius and door clear widths are measured at survey, and where they fail the options are crane hoisting under traffic police permission in a night window, or forming a temporary structural opening in an external wall and closing it afterwards. Both carry approvals and belong in the programme from week one.

Shielding in a building where everything is occupied

Shielding design precedes civil work everywhere. In Mumbai it also tends to produce thicker barriers, and the reason is occupancy.

Lead equivalence is calculated barrier by barrier from workload, operating potential, distance, the occupancy factor of the space beyond and the shielding design goal for it. In a freestanding block flanked by plant rooms and lightly used corridors, several barriers are defensible at the lower end of the usual 1.5-2 mm Pb band. A lab inserted into a live floor plate rarely has that luxury: ward on one side, waiting area on another, consulting rooms above and day-care below is a six-sided problem in which nearly every neighbour is a fully occupied uncontrolled area at short distance. Barriers then sit at the top of the band, occasionally 2.5-3 mm Pb, with door and lead glass specifications rising alongside, so an identical clinical room can differ materially between two floors of the same hospital. Floor and ceiling barriers matter here too, and where a floor above is leased or the building shared, that occupancy assumption is the hospital’s to justify.

The AERB pathway, described honestly

AERB regulates the room as a radiation installation and revises its processes periodically, so what follows is the shape of the pathway; confirm current requirements, forms and fees on eLORA at the time of submission.

Typically the hospital registers as an institution on eLORA, then submits the room layout with barrier-by-barrier shielding details for layout approval before construction begins. The imaging model and supplier generally need to sit within AERB type approval, and the facility nominates a Radiological Safety Officer — certification runs on fixed examination cycles, so it starts earliest and finishes last. After OEM installation and acceptance testing, QA testing and a radiation survey at every barrier, door edge, window frame and console position support the licence application.

The licence is issued to the hospital, not the contractor, and nobody can honestly promise an approval. What we own is everything AERB reads: layout drawing, shielding calculations, adjoining-occupancy mapping, and coordination of QA and survey. In Mumbai that occupancy mapping attracts the most queries, because dense buildings have complicated neighbours. Budget three to six months of regulatory lead time, concurrent with construction.

Coastal air and two separate HVAC problems

The procedure room needs 21-24°C at 40-60% RH with HEPA-filtered positive pressure, and a Mumbai summer design wet bulb of 27-28°C makes that a latent-load problem: deeper coil, lower chilled water temperature, reheat downstream, fresh air pre-treated in its own dehumidification stage. Humidity is not comfort here — low RH raises static discharge risk around sensitive electronics, high RH risks condensation inside expensive equipment. Near the coast, coil fins get coated and terrace plant moves to marine-grade casing.

The technical room is a different problem: 5-15 kW rejected continuously whether or not a case is running, inside a narrow band commonly 18-25°C, with a hard limit at which the system throttles or shuts down. It needs dedicated redundant cooling on essential power, not a spare split. And because the shielded envelope is close to airtight, every duct crossing a lead barrier needs a baffled penetration drawn on the shielding layout rather than improvised on site.

Programme, statutory notes and delivery from Pune

A single-plane lab inside an existing shell runs 16-24 weeks from order to clinical handover; a Mumbai retrofit in a live hospital adds two to six weeks for phasing, containment agreed with infection control, and noise windows, since hospital precincts are silence zones and core cutting is confined to daytime hours while material moves at night. Biplane and hybrid projects run 26-36 weeks. Long-lead imaging delivery, where it exceeds these windows, governs everything — which is why the purchase order and the AERB layout submission belong in the same month.

Beyond AERB, any change to built form routes through the MCGM building proposal process, and a fire NOC is required under the Maharashtra Fire Prevention and Life Safety Measures Act because a new interventional suite alters compartmentation and fire load. Facility registration sits with the civic public health department, and hospitals claiming cardiac packages under MJPJAY or PM-JAY must evidence supporting infrastructure.

Mumbai is about 150 km from Pune — a same-day survey city and a next-day escalation city. Design and the regulatory package are produced in Pune, specialist trades travel, general civil labour is engaged locally. Pune is our only office, and we say so.

Full technical specification

Barrier calculation method, room sizing, power and UPS detail and the full AERB sequence are set out on the parent cath lab setup service page. This page covers what changes in Mumbai.

Cath Lab Setup cost in Mumbai

The imaging system dominates a cath lab budget and is priced by the OEM, not by the city, so a new mid-range single-plane lab in Mumbai still plans at the national ₹3.5-5.5 crore all-in. What Mumbai moves is the infrastructure envelope around it — civil and modular interiors, shielding, precision HVAC, UPS and gas — which typically runs 15-25 percent above the national ₹75 lakh to ₹1.5 crore band, landing nearer ₹90 lakh to ₹1.8 crore. Dense adjoining occupancy pushing barriers toward 2.5-3 mm Pb, restricted working hours, hand-carried material movement and extra dehumidification capacity are the four line items doing that. Indicative planning ranges, not quotations.

Indicative planning range only. Final pricing follows a site survey and detailed scope. Request a quotation →

Local Landscape

Healthcare institutions in and around Mumbai

Major hospitals and medical institutions in the Mumbai catchment — the infrastructure environment our teams work in.

Asian Heart Institute, Bandra Kurla Complex
Sir H. N. Reliance Foundation Hospital, Girgaon
Gleneagles Hospital, Parel
Breach Candy Hospital Trust, Bhulabhai Desai Road
Wockhardt Hospitals, Mumbai Central
Dr. L. H. Hiranandani Hospital, Powai
Holy Family Hospital, Bandra
Saifee Hospital, Charni Road

Institutions listed for local context only. Reference does not imply a commercial relationship or endorsement.

FAQ

Cath Lab Setup in Mumbai — FAQs

Questions hospital teams in Mumbai ask most often.

Can a cath lab be retrofitted into an existing Mumbai hospital floor?

Usually, but three checks decide it and all three are structural. Slab-to-slab height below roughly 3.2 m rules out a ceiling-mounted gantry, which is the most common disqualifier in buildings from the 1990s and 2000s. Floor and slab capacity must be verified against the OEM point-load schedule, because the ceiling grid concentrates gantry and monitor loads into a handful of anchors rather than spreading them. And the cable route between technical room and gantry needs either a trench or a raised floor, which itself consumes height you may already be short of. All three are survey questions, not site questions.

How do you get a cath lab gantry into a building in south Mumbai?

By planning it in week one, not month four. The gantry stand and table plinth are the largest indivisible items in the project and do not knock down the way modular panels do, so lift car dimensions, lift capacity, staircase turning radius and door clear widths are all measured at survey. Where the lift cannot take them, the options are crane hoisting with traffic police permission and a night road window, or forming a temporary structural opening in an external wall and closing it afterwards. Both are civil scope with their own approvals and both belong in the programme before the equipment ships.

Does radiation shielding cost more in a Mumbai hospital?

Generally yes, and for a defensible engineering reason rather than a pricing one. Lead equivalence is calculated barrier by barrier from workload, distance, the occupancy factor of the space beyond, and the shielding design goal for that space. A lab wedged into an occupied floor plate with wards, waiting areas and consulting suites on adjacent sides, and occupied floors above and below, is a six-sided problem in which nearly every neighbour is a fully occupied uncontrolled area at short distance. Barriers that would sit at 1.5 mm Pb in a freestanding block then land at 2 mm and occasionally 2.5-3 mm.

What approvals beyond AERB does a Mumbai cath lab need?

Any change to built form or floor area routes through the MCGM building proposal process, and a fire NOC is required under the Maharashtra Fire Prevention and Life Safety Measures Act because a new interventional suite alters compartmentation, egress and fire load. Facility registration sits with the civic public health department. If the hospital treats cardiac packages under MJPJAY or Ayushman Bharat PM-JAY, the state health department examines whether the infrastructure supports what is being claimed. AERB layout approval and licensing run alongside all of it, on their own clock, and the licence is issued to the hospital.

Do you have an office in Mumbai?

No. Pune is our only office, and every Mumbai project is run from there with supervision resident in the city for the duration of installation. Mumbai is roughly 150 km down the expressway, which makes it a same-day survey city and a next-day escalation city. Shielding design, OEM drawing reconciliation and the AERB submission package are prepared in Pune; lead lining, modular interiors, HVAC, UPS and gas are executed on site with specialist trades travelling from Pune and general civil labour engaged locally. We would rather state that plainly than imply a branch presence we do not have.

Planning a cath lab setup project in Mumbai?

Send us your drawings or requirements and our team will revert with a scope, timeline, and budget estimate. Site surveys across Maharashtra are arranged from our Pune office.